A cooling system has a controller (reliability 0.98) in series with a pair of identical pumps in parallel, each with reliability 0.90; the system works if the controller and at least one pump work. What is the system reliability?
- A. 0.7938
- B. 0.8820
- C. 0.9900
- D. 0.9702
Correct answer: D. 0.9702
Pump pair = 1 − (0.10 × 0.10) = 0.99. System = 0.98 × 0.99 = 0.9702. Treating everything as series gives 0.98 × 0.9 × 0.9 = 0.7938; one pump only gives 0.882; 0.99 forgets the controller.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A packing line has three stages in series: a feeder (reliability 0.95), a sealing stage with two identical sealers in parallel (each 0.80…
- A critical sensor has reliability 0.85. Identical sensors can be installed in parallel (the stage works if at least one works). What is…
- A buyer uses a single sampling plan: inspect n = 20 items from each lot and accept the lot if at most c = 1 is defective. If a lot is 5%…
- Lots of N = 1,000 are checked with the plan n = 20, c = 1. Rejected lots are screened 100% and all defectives replaced; in accepted lots…
- Match each acceptance-sampling term with its meaning. 1. AQL 2. LTPD 3. Producer's risk (α) 4. Consumer's risk (β) a. Probability of…
- A sampling plan inspects n = 50 items and accepts the lot if c ≤ 2 defectives are found. Using the Poisson approximation, what is the…