For an in-control process using 3-sigma limits, about how many samples will be plotted, on average, before a false out-of-control signal?
- A. About 27
- B. About 100
- C. About 3
- D. About 370
Correct answer: D. About 370
The chance of a point outside 3-sigma limits is 0.0027, and the average run length is 1/p ≈ 370. 27 comes from confusing 0.27% with 2.7%.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- An X̄ chart with 3-sigma limits uses samples of n = 4. The process mean suddenly shifts up by one process standard deviation (1σ). What is…
- Daily demand is independent from day to day and lead time is constant. If the supplier's lead time doubles from 8 to 16 days, with the…
- A plant needs to produce 5,000 units of P (1.2 machine-hours each) and 8,000 units of Q (0.75 machine-hours each) a year, plus a setup…
- An online lender approves 400 loans a week and has, on average, 1,000 applications in process. It wants to grow to 600 approvals a week…
- A firm's accounts receivable average ₹90 lakh, and credit sales are ₹6 crore a year (360 days). It wants to cut average receivables to ₹60…
- Machine A has a design capacity of 120 units/day, effective capacity 100, actual output 90. Machine B has a design capacity of 100…