Daily demand is independent from day to day and lead time is constant. If the supplier's lead time doubles from 8 to 16 days, with the same service level, what happens to the safety stock?

  1. A. It rises by about 41%
  2. B. It doubles, in line with lead time
  3. C. It rises by 4 times
  4. D. It is unchanged

Correct answer: A. It rises by about 41%

Safety stock = z σ_d √L, so it scales with the square root of lead time: √2 ≈ 1.414, a 41% rise. The reorder point's cycle-stock part (d × L) does double, but safety stock does not.