Management & CommerceVery hardOps MT · MBA placement
A line's tasks total 4.2 minutes of work per unit, and the longest single task takes 0.9 minutes. The line will have exactly 6 stations and runs 420 productive minutes a day. Even if tasks could be grouped perfectly, what is the maximum daily output?
- A. 600 units
- B. 100 units
- C. 700 units
- D. 466 units
Correct answer: D. 466 units
Perfect balance would give a cycle time of 4.2/6 = 0.7 min, but no station can cycle faster than its longest indivisible task, 0.9 min. Output = 420/0.9 ≈ 466 units. The trap 600 uses the 0.7-minute cycle.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Activities (days; immediate predecessors): A 3 (–), B 5 (–), C 4 (A), D 2 (A, B), E 6 (C), F 3 (D), G 4 (E, F). A new method can cut…
- A project has a budget at completion of ₹100 lakh. At the end of month 6 the planned value is ₹50 lakh, the earned value ₹40 lakh and the…
- A project has a single critical path of 20 days and no other path longer than 12 days. Indirect costs are ₹5,000 a day. Activities on the…
- Maximise Z = 4x + 3y subject to 2x + y ≤ 20, x + 3y ≤ 30, x ≤ 8, x, y ≥ 0. What is the optimal value of Z, and which constraint is not…
- Maximise Z = 4x + 5y subject to x + y ≤ 8, x + 3y ≤ 18, x, y ≥ 0. The optimum is x = 3, y = 5. Keeping everything else fixed, over what…
- A refinery makes products A (x litres) and B (y litres). Management insists that A must be at least 30% of total output. Which linear…