Activities (days; immediate predecessors): A 3 (–), B 5 (–), C 4 (A), D 2 (A, B), E 6 (C), F 3 (D), G 4 (E, F). A new method can cut activity E from 6 days to 1 day. What will the project duration become?

  1. A. 12 days
  2. B. 17 days
  3. C. 15 days
  4. D. 14 days

Correct answer: D. 14 days

Paths: A–C–E–G = 17, B–D–F–G = 14, A–D–F–G = 12. Cutting E by 5 days drops A–C–E–G to 12, but B–D–F–G (14 days) now becomes critical, so the project takes 14 days, not 17 − 5 = 12.