Activities (days; immediate predecessors): A 3 (–), B 5 (–), C 4 (A), D 2 (A, B), E 6 (C), F 3 (D), G 4 (E, F). A new method can cut activity E from 6 days to 1 day. What will the project duration become?
- A. 12 days
- B. 17 days
- C. 15 days
- D. 14 days
Correct answer: D. 14 days
Paths: A–C–E–G = 17, B–D–F–G = 14, A–D–F–G = 12. Cutting E by 5 days drops A–C–E–G to 12, but B–D–F–G (14 days) now becomes critical, so the project takes 14 days, not 17 − 5 = 12.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A project has a budget at completion of ₹100 lakh. At the end of month 6 the planned value is ₹50 lakh, the earned value ₹40 lakh and the…
- A project has a single critical path of 20 days and no other path longer than 12 days. Indirect costs are ₹5,000 a day. Activities on the…
- Maximise Z = 4x + 3y subject to 2x + y ≤ 20, x + 3y ≤ 30, x ≤ 8, x, y ≥ 0. What is the optimal value of Z, and which constraint is not…
- Maximise Z = 4x + 5y subject to x + y ≤ 8, x + 3y ≤ 18, x, y ≥ 0. The optimum is x = 3, y = 5. Keeping everything else fixed, over what…
- A refinery makes products A (x litres) and B (y litres). Management insists that A must be at least 30% of total output. Which linear…
- In the optimal LP solution of a product-mix problem, product T is not produced and its reduced cost is −₹6 per unit. What does this mean?