Management & CommerceModerateOps MT · MBA placement
An online lender approves 400 loans a week and has, on average, 1,000 applications in process. It wants to grow to 600 approvals a week without increasing the applications in process. What must happen to average processing time?
- A. Fall from 2.5 weeks to 1.5 weeks
- B. Fall from 2.5 weeks to about 1.67 weeks
- C. Stay at 2.5 weeks, since Little's law fixes it
- D. Rise from 2.5 weeks to 3.75 weeks
Correct answer: B. Fall from 2.5 weeks to about 1.67 weeks
Little's law W = L/λ: today 1,000/400 = 2.5 weeks; target 1,000/600 ≈ 1.67 weeks. Keeping W at 2.5 would raise WIP to 1,500; 3.75 weeks would mean even more WIP.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A firm's accounts receivable average ₹90 lakh, and credit sales are ₹6 crore a year (360 days). It wants to cut average receivables to ₹60…
- Machine A has a design capacity of 120 units/day, effective capacity 100, actual output 90. Machine B has a design capacity of 100…
- A line's tasks total 4.2 minutes of work per unit, and the longest single task takes 0.9 minutes. The line will have exactly 6 stations…
- Activities (days; immediate predecessors): A 3 (–), B 5 (–), C 4 (A), D 2 (A, B), E 6 (C), F 3 (D), G 4 (E, F). A new method can cut…
- A project has a budget at completion of ₹100 lakh. At the end of month 6 the planned value is ₹50 lakh, the earned value ₹40 lakh and the…
- A project has a single critical path of 20 days and no other path longer than 12 days. Indirect costs are ₹5,000 a day. Activities on the…