A plant needs to produce 5,000 units of P (1.2 machine-hours each) and 8,000 units of Q (0.75 machine-hours each) a year, plus a setup allowance of 10% of run time. Each machine works 2,000 hours a year at 80% utilisation. How many machines are needed?

  1. A. 8
  2. B. 7
  3. C. 9
  4. D. 6

Correct answer: C. 9

Run hours = 5,000 × 1.2 + 8,000 × 0.75 = 12,000; with setups 13,200 hours. Effective hours per machine = 2,000 × 0.8 = 1,600, so 13,200/1,600 = 8.25 → round up to 9. Ignoring setups gives 7.5 → 8, ignoring the 80% utilisation gives 6.6 → 7, and ignoring both gives 6.