Daily demand is a steady 50 units, the order quantity is 200 units, and the supplier's lead time is 10 days. At what on-hand stock level should a new order be placed (no safety stock)?
- A. 500 units
- B. 300 units, with one order outstanding
- C. 0 units, since lead time exceeds the order cycle
- D. 100 units, with two orders already outstanding
Correct answer: D. 100 units, with two orders already outstanding
Lead-time demand is 50 × 10 = 500, so the reorder point in inventory position is 500. Each cycle lasts 200/50 = 4 days, so 2 earlier orders (400 units) are always in the pipeline when you reorder: on-hand = 500 − 400 = 100.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Lead-time demand is normal with a standard deviation of 40 units, and the firm holds 60 units of safety stock. What cycle-service level…
- Product X (lead time 1 week) needs 2 units of Y; Y (lead time 2 weeks) needs 3 units of Z; Z has a lead time of 1 week. 100 units of X are…
- Four jobs wait at one machine (processing hours; weight = importance): A (4; 1), B (2; 3), C (6; 2), D (3; 3). Using the weighted shortest…
- Seven jobs taking 8, 7, 6, 5, 4, 3 and 2 hours are to be run on three identical parallel machines. Using the longest-processing-time (LPT)…
- A machine has a mean time between failures of 400 hours and a mean time to repair of 20 hours. What is its steady-state availability?
- A pump fails at random (constant failure rate) with a mean time between failures of 400 hours. What is the probability that it runs a…