A Six Sigma team is analysing a late-delivery problem. In which DMAIC phase would it normally carry out a measurement system analysis (gauge R&R) and establish the baseline sigma level?
- A. Measure
- B. Define
- C. Improve
- D. Control
Correct answer: A. Measure
Define sets the problem and scope; Measure validates the measurement system and establishes the baseline; Analyse finds root causes; Improve tests solutions; Control sustains them with control plans and charts.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Activity A takes 5 days. Activity B takes 4 days and has two links with A: it can start no earlier than 2 days after A starts…
- At a project review, earned value is ₹40 lakh, planned value ₹50 lakh and actual cost ₹35 lakh. Which statement is correct?
- A maximisation LP has 3 '≤' constraints and 4 decision variables. After adding slack variables, how many variables are basic in any basic…
- A resource's shadow price in an LP is ₹12 per hour, valid for right-hand-side values between 80 and 140 hours; the current availability is…
- For a decision, the expected value of perfect information is ₹18 lakh and the expected value of the sample information from a proposed…
- A supplier's lead time is uniformly distributed between 4 and 10 days. What is the probability that a given order takes more than 8 days…