Management & CommerceVery hardOps MT · MBA placement
A plant runs at 80% utilisation and its average queue of jobs is 4 hours of work. Management plans to load it to 95% utilisation. Assuming M/M/1-like behaviour, roughly how will waiting time change?
- A. It will rise about 4.75 times, to roughly 19 hours
- B. It will rise about 19%, in line with utilisation
- C. It will roughly double, to 8 hours
- D. It will stay about the same because capacity is unchanged
Correct answer: A. It will rise about 4.75 times, to roughly 19 hours
In M/M/1, waiting time ∝ ρ/(1 − ρ): 0.8/0.2 = 4 versus 0.95/0.05 = 19, a 4.75-fold rise. Queues explode non-linearly as utilisation nears 100%, which is why planners keep a capacity cushion.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A supply chain shares point-of-sale data and builds a joint forecast with its retailer, agreeing on replenishment plans together. Which…
- A lean programme wants to halve a part's economic lot size without changing demand or holding cost. By how much must the setup (ordering)…
- A part is made in lots of 1,200 at a production rate of 100 per day, while it is used at 40 per day throughout the year. In each…
- Three stations in series each take 1 minute per unit. A batch of 50 units moves from station to station only when the whole batch is done…
- An audit of 2,000 invoices finds 96 errors. Each invoice has 8 distinct fields where an error can occur. What is the DPMO?
- Match each situation with the most suitable control chart. 1. Number of scratches per car body (same body size each time) 2. Defects per…