A lean programme wants to halve a part's economic lot size without changing demand or holding cost. By how much must the setup (ordering) cost per lot be reduced?

  1. A. By 50%
  2. B. By 75%
  3. C. By about 29%
  4. D. By 25%

Correct answer: B. By 75%

EOQ ∝ √S, so halving the EOQ needs S to fall to a quarter: a 75% cut. A 50% cut in setup cost reduces the lot size only by about 29% (to 1/√2).