Management & CommerceHardOps MT · MBA placement
A machine runs batches of 100 units at 1 minute per unit. A SMED project cuts the changeover from 60 to 20 minutes, and the batch size is kept at 100. By how much does hourly capacity rise?
- A. About 33%
- B. About 67%
- C. About 25%
- D. Nil, because run time per unit is unchanged
Correct answer: A. About 33%
Capacity = 100/(setup + 100) per minute: 100/160 → 37.5 per hour; 100/120 → 50 per hour, a rise of about 33%. The 67% figure is the cut in setup time itself, not the capacity gain.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A single-server help desk (M/M/1) receives 8 requests an hour and serves 10 an hour. If the server's speed is doubled to 20 an hour, what…
- A contact centre receives 120 calls an hour, and calls last 3 minutes on average. What is the offered traffic load in Erlangs, and what…
- Demand grows by exactly 10 units every period. Simple exponential smoothing with α = 0.2 has been used for a long time. Once things…
- A process has Cp = 2.0 (spec limits ±6σ) and its mean then drifts by 1.5σ, as assumed in Six Sigma tables. What is its Cpk?
- A p-chart is used for a process with p̄ = 0.05. What is the smallest sample size that gives a positive lower control limit with 3-sigma…
- A project's critical path is 120 days long, but the contract requires completion in 110 days. When CPM is computed backward from the…