A machine runs batches of 100 units at 1 minute per unit. A SMED project cuts the changeover from 60 to 20 minutes, and the batch size is kept at 100. By how much does hourly capacity rise?

  1. A. About 33%
  2. B. About 67%
  3. C. About 25%
  4. D. Nil, because run time per unit is unchanged

Correct answer: A. About 33%

Capacity = 100/(setup + 100) per minute: 100/160 → 37.5 per hour; 100/120 → 50 per hour, a rise of about 33%. The 67% figure is the cut in setup time itself, not the capacity gain.