Management & CommerceHardOps MT · MBA placement
A contact centre receives 120 calls an hour, and calls last 3 minutes on average. What is the offered traffic load in Erlangs, and what does it mean?
- A. 40 Erlangs – about 40 calls arrive per agent each hour
- B. 6 Erlangs – on average 6 agents are busy at once
- C. 0.05 Erlangs – each call takes up 5% of an hour of capacity
- D. 360 Erlangs – the total call-minutes offered per hour
Correct answer: B. 6 Erlangs – on average 6 agents are busy at once
Offered load = arrival rate × average handling time = 120 × 3/60 = 6 Erlangs. It is the average number of simultaneously busy servers, so more than 6 agents are needed for a stable queue.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Demand grows by exactly 10 units every period. Simple exponential smoothing with α = 0.2 has been used for a long time. Once things…
- A process has Cp = 2.0 (spec limits ±6σ) and its mean then drifts by 1.5σ, as assumed in Six Sigma tables. What is its Cpk?
- A p-chart is used for a process with p̄ = 0.05. What is the smallest sample size that gives a positive lower control limit with 3-sigma…
- A project's critical path is 120 days long, but the contract requires completion in 110 days. When CPM is computed backward from the…
- Three activities have PERT estimates (optimistic, most likely, pessimistic) in days: P (2, 5, 14), Q (4, 6, 8), R (1, 8, 9). Which…
- An LP has the constraints x + y ≤ 10, x ≤ 6 and 2x + 2y ≤ 30, with x, y ≥ 0. Which constraint is redundant?