Management & CommerceHardOps MT · MBA placement
On the product–process matrix, which pairing is most typical?
- A. Low-volume, high-variety products with a continuous-flow process
- B. High-volume standard products with a job-shop process
- C. One-off projects with an assembly line
- D. Low-volume, high-variety custom products with a job-shop process
Correct answer: D. Low-volume, high-variety custom products with a job-shop process
The matrix pairs one-off products with projects, low-volume high-variety work with job shops, batches with batch processes, high-volume standard products with assembly lines, and commodities with continuous flow. Off-diagonal positions usually carry cost or flexibility penalties.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Demand requires a takt time of 45 seconds, but the bottleneck station's work content is 50 seconds and cannot be split. What is the…
- Four jobs wait at one machine (processing days; due day): A (3; 5), B (2; 4), C (4; 12), D (5; 9). What is the maximum lateness under the…
- A control system has three identical sensors, each with reliability 0.9, and it works if at least two of the three work (independent…
- A planner computes the EOQ using an annual demand forecast that turns out to be 50% too high (true demand is two-thirds of the forecast)…
- At a single-server counter (M/M/1) with λ = 6 per hour and μ = 8 per hour, what is the difference between the average number in the system…
- A line's tasks total 40 minutes of work per unit and the cycle time is 6 minutes. Precedence constraints force the planner to use 8…