An assembly line has 8 tasks totalling 230 seconds; the longest task, which cannot be split, takes 55 seconds. A shift is 8 hours with 30 minutes of breaks, and demand is 540 units a shift. With no parallel stations and no task splitting, what is the maximum output per shift?

  1. A. 540 units
  2. B. 490 units
  3. C. 586 units
  4. D. 523 units

Correct answer: B. 490 units

Takt = 27,000 s ÷ 540 = 50 s, but no station's cycle can be below the 55-second task, so output ≤ 27,000 ÷ 55 = 490.9 → 490 units. 523 forgets to deduct breaks (28,800 ÷ 55); 540 ignores the indivisible task.