Management & CommerceHardMBA Placement · Ops MT
An assembly line has 8 tasks totalling 230 seconds; the longest task, which cannot be split, takes 55 seconds. A shift is 8 hours with 30 minutes of breaks, and demand is 540 units a shift. With no parallel stations and no task splitting, what is the maximum output per shift?
- A. 540 units
- B. 490 units
- C. 586 units
- D. 523 units
Correct answer: B. 490 units
Takt = 27,000 s ÷ 540 = 50 s, but no station's cycle can be below the 55-second task, so output ≤ 27,000 ÷ 55 = 490.9 → 490 units. 523 forgets to deduct breaks (28,800 ÷ 55); 540 ignores the indivisible task.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Three stages run in series. Stage A can process 100 units/hour and scraps 5% of what it processes; B can process 90/hour and scraps 10%; C…
- A project has activities A (3 days) and B (2 days), which start at once; C (8 days) follows A; D (2 days) follows B; E (3 days) follows D…
- A project has two independent paths that both end the project: A (6 days) then C (5 days), and B (8 days) then D (2 days). Crash costs and…
- A firm moves 36,500 units a year of a ₹2,000 part. Sea freight takes 6 days in transit; air takes 1 day. The buyer owns goods in transit…
- A warehouse ships SKU P at 300 units/day and holds on average 1,200 units of it; SKU Q ships 100 units/day with 1,000 units on hand on…
- A single-server M/M/1 counter has utilisation 0.8. Demand grows so utilisation becomes 0.9 with the same service rate. By what factor does…