Management & CommerceHardMBA Placement · Ops Analyst
Three stages run in series. Stage A can process 100 units/hour and scraps 5% of what it processes; B can process 90/hour and scraps 10%; C can process 85/hour and scraps 2%. Scrap is removed after each stage and capacities refer to units processed. How many good units per hour leave C?
- A. 71.2
- B. 83.3
- C. 79.4
- D. 88.2
Correct answer: C. 79.4
A sends 95 good units; B processes 90 (its cap) and passes 81; C has spare capacity, processes 81 and passes 81 × 0.98 = 79.4. 71.2 wrongly applies all yields to C's 85; 83.3 treats C as the bottleneck; 88.2 ignores B's scrap.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A project has activities A (3 days) and B (2 days), which start at once; C (8 days) follows A; D (2 days) follows B; E (3 days) follows D…
- A project has two independent paths that both end the project: A (6 days) then C (5 days), and B (8 days) then D (2 days). Crash costs and…
- A firm moves 36,500 units a year of a ₹2,000 part. Sea freight takes 6 days in transit; air takes 1 day. The buyer owns goods in transit…
- A warehouse ships SKU P at 300 units/day and holds on average 1,200 units of it; SKU Q ships 100 units/day with 1,000 units on hand on…
- A single-server M/M/1 counter has utilisation 0.8. Demand grows so utilisation becomes 0.9 with the same service rate. By what factor does…
- An item has 50 units on hand at the start of week 1. The master schedule has receipts of 100 in week 1 and 100 in week 3. Customer orders…