Quantitative AptitudeModerateSSC CGL · RRB NTPC · IBPS
A and B together can do a job in 12 days. A alone can do it in 30 days. How long will B alone take?
- A. 18 days
- B. 25 days
- C. 21 days
- D. 20 days
Correct answer: D. 20 days
1/B = 1/12 − 1/30 = 18/360, so B takes 20 days.
More Time and Work questions
- A pipe can fill a tank in 8 hours and an outlet can empty the full tank in 24 hours. If both are opened together on an empty tank, how…
- 8 workers can build a wall in 15 days. How many days will 5 workers (working at the same rate) take?
- A can do a work in 18 days and B in 9 days. They complete it together and are paid ₹3000. What is A's share?
- A, B and C can do a job alone in 15, 30 and 10 days respectively. In how many days will they finish it working together?
- 4 men working 8 hours a day can finish a job in 20 days. If they work only 5 hours a day, how many days will they take?
- Priya can complete a job in 45 days and Neha alone can complete it in 90 days. In how many days will they finish it together?