8 workers can build a wall in 15 days. How many days will 5 workers (working at the same rate) take?

  1. A. 26 days
  2. B. 24 days
  3. C. 9 days
  4. D. 20 days

Correct answer: B. 24 days

Total work = 8 × 15 = 120 man-days. With 5 workers: 120/5 = 24 days.