CS FundamentalsHardAccenture · Scrum interview
At the end of a sprint, one backlog item is coded but its automated tests, required by the Definition of Done, are not written. What does the Scrum Guide say about it?
- A. It can be shown in the Sprint Review as 90% done
- B. It is released and the tests are added next sprint
- C. Its points count towards velocity because coding is the main effort
- D. It is not part of the Increment and cannot be presented as done; it returns to the Product Backlog for future consideration
Correct answer: D. It is not part of the Increment and cannot be presented as done; it returns to the Product Backlog for future consideration
Work that does not meet the Definition of Done is not part of the Increment; it goes back to the Product Backlog. 'Almost done' work hides undone effort and quality debt.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A sprint commitment had stories of 8, 5, 5, 3 and 3 points. At the sprint's end the 8, one 5 and both 3s meet the Definition of Done; the…
- Mid-sprint, the Product Owner asks the Developers to also add a small new item. The Sprint Goal is not at risk. What does Scrum allow?
- For a one-month sprint the Scrum Guide sets maximum timeboxes of 8 hours for Sprint Planning, 4 hours for the Sprint Review and 3 hours…
- How many of these are Extreme Programming (XP) practices: (1) pair programming, (2) collective code ownership, (3) continuous integration…
- A backlog contains: 'As a developer, I want to create the database tables for orders.' Which INVEST criterion does it most clearly fail…
- What is the key difference between the incremental and the iterative approaches?