Electrical EngineeringModerate

A plant has a maximum demand of 50 MW and supplies 1.8 x 10^8 kWh in a year (8760 h). The load factor is about

  1. A. 41%
  2. B. 80%
  3. C. 20%
  4. D. 100%

Correct answer: A. 41%

Average load = 1.8e8 / 8760 = 20,548 kW; LF = 20.55 / 50 = 0.411.