Electrical EngineeringHard

A plant has a maximum demand of 25 MW and supplies 87600 MWh in a year of 8760 h. Its load factor is

  1. A. 43.8 %
  2. B. 0.4 %
  3. C. 40 %
  4. D. 9.6 %

Correct answer: C. 40 %

Average load = 87600/8760 = 10.00 MW; LF = avg/max = 40.0 %.