Electrical EngineeringHard
A plant has a maximum demand of 25 MW and supplies 87600 MWh in a year of 8760 h. Its load factor is
- A. 43.8 %
- B. 0.4 %
- C. 40 %
- D. 9.6 %
Correct answer: C. 40 %
Average load = 87600/8760 = 10.00 MW; LF = avg/max = 40.0 %.
Practise more Power Systems & Protection (Electrical) questionsPower Systems & Protection (Electrical): notes and key points
More Power Systems & Protection (Electrical) questions
- Three consumer groups have maximum demands of 400 kW, 350 kW and 100 kW. The maximum demand on the station (coincident) is 600 kW. The…
- A power station of installed capacity 200 MW has a maximum demand of 180 MW and generates 1200000 MWh in a year. Its utilisation factor…
- A power station of installed capacity 300 MW has a maximum demand of 240 MW and generates 1350000 MWh in a year. Its utilisation factor…
- A consumer's load is 1000 kW at 0.75 lagging. After installing a capacitor bank to improve the pf to 0.95 lagging, the reduction in kVA…
- A generator of 500 MVA has an inertia constant H = 4 MJ/MVA. The kinetic energy stored in its rotor at synchronous speed is
- A generator delivering Pm = 0.3 of its maximum power transfer capacity Pmax (pre-fault) suffers a 3-phase fault at its terminals (so Pe =…