Electrical EngineeringHard
A power station of installed capacity 200 MW has a maximum demand of 180 MW and generates 1200000 MWh in a year. Its utilisation factor (maximum demand/installed capacity) is
- A. 90 %
- B. 68.49 %
- C. 0.9 %
- D. 10 %
Correct answer: A. 90 %
Max demand/capacity = 180/200 = 90.0 %. (Standard formula applied.)
Practise more Power Systems & Protection (Electrical) questionsPower Systems & Protection (Electrical): notes and key points
More Power Systems & Protection (Electrical) questions
- A power station of installed capacity 300 MW has a maximum demand of 240 MW and generates 1350000 MWh in a year. Its utilisation factor…
- A consumer's load is 1000 kW at 0.75 lagging. After installing a capacitor bank to improve the pf to 0.95 lagging, the reduction in kVA…
- A generator of 500 MVA has an inertia constant H = 4 MJ/MVA. The kinetic energy stored in its rotor at synchronous speed is
- A generator delivering Pm = 0.3 of its maximum power transfer capacity Pmax (pre-fault) suffers a 3-phase fault at its terminals (so Pe =…
- A single-core cable has conductor radius 1 cm, sheath internal radius 1.5 cm and insulation of relative permittivity 3. For a 10 km length…
- A single-core cable for a 11 kV (line) 3-phase system has conductor radius 1.5 cm and sheath radius 3 cm. The maximum electric stress in…