Electrical EngineeringHard

A power station of installed capacity 200 MW has a maximum demand of 180 MW and generates 1200000 MWh in a year. Its utilisation factor (maximum demand/installed capacity) is

  1. A. 90 %
  2. B. 68.49 %
  3. C. 0.9 %
  4. D. 10 %

Correct answer: A. 90 %

Max demand/capacity = 180/200 = 90.0 %. (Standard formula applied.)