A power station of installed capacity 300 MW has a maximum demand of 240 MW and generates 1350000 MWh in a year. Its utilisation factor (maximum demand/installed capacity) is

  1. A. 51.37 %
  2. B. 20 %
  3. C. 0.8 %
  4. D. 80 %

Correct answer: D. 80 %

Max demand/capacity = 240/300 = 80.0 %. (Standard formula applied.)