Management & CommerceVery hardOps MT · Supply chain · MBA placement pattern
Quarterly demand is 1,400, 2,000, 1,800 and 2,000 units. Each worker makes 100 units a quarter and the firm starts with 15 workers. Hiring costs ₹3,000 per worker, a layoff ₹5,000 per worker, and holding ₹50 per unit per quarter on ending inventory. Plan 1 (chase) matches output to demand each quarter. Plan 2 (level) sets one constant workforce from Q1 that meets total demand with no shortages. Regular wages are the same in both plans. Which plan is cheaper, and by how much?
- A. Chase, by ₹10,000
- B. Level, by ₹10,000
- C. Chase, by ₹1,000
- D. Level, by ₹6,000
Correct answer: A. Chase, by ₹10,000
Chase: workers needed 14, 20, 18, 20 → lay off 1, hire 6, lay off 2, hire 2. Cost = 8 × 3,000 + 3 × 5,000 = ₹39,000. Level: 7,200 ÷ 4 = 1,800 a quarter = 18 workers (hire 3 = ₹9,000). Ending inventory 400, 200, 200, 0 → 800 × 50 = ₹40,000. Level total = ₹49,000, so chase is cheaper by ₹10,000. Forgetting the level plan's hiring cost shrinks the gap to ₹1,000. Both plans use 72 worker-quarters, so wages cancel.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A firm produces at a constant rate equal to average demand. Quarterly demand is 1,000, 1,400, 1,600 and 1,200 units, and there is no…
- For one week, an item's gross requirement is 120 units. On-hand stock is 35, a scheduled receipt of 25 is due that week, and the firm…
- Product A needs 2 units of B and 3 units of C. Each B needs 2 units of D; each C needs 1 unit of D and 4 units of E. An order for 50 A…
- Each unit of X needs 2 Y and 1 Z. Each Y needs 3 W. Each Z needs 2 W and 1 Y. With no stock on hand, how many units of W are needed for 40…
- Net requirements over six weeks are 50, 60, 70, 60, 95 and 75 units. Setup cost is ₹200 per order and holding cost is ₹1 per unit per…
- An item has gross requirements of 40, 0, 60, 30, 0 and 80 units in weeks 1–6. On-hand stock is 50, a scheduled receipt of 20 arrives in…