For one week, an item's gross requirement is 120 units. On-hand stock is 35, a scheduled receipt of 25 is due that week, and the firm keeps safety stock of 10. What is the net requirement?
- A. 60
- B. 70
- C. 50
- D. 95
Correct answer: B. 70
Net requirement = gross − on hand − scheduled receipts + safety stock = 120 − 35 − 25 + 10 = 70. Leaving out safety stock gives 60, subtracting it gives 50, and forgetting the scheduled receipt gives 95.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Product A needs 2 units of B and 3 units of C. Each B needs 2 units of D; each C needs 1 unit of D and 4 units of E. An order for 50 A…
- Each unit of X needs 2 Y and 1 Z. Each Y needs 3 W. Each Z needs 2 W and 1 Y. With no stock on hand, how many units of W are needed for 40…
- Net requirements over six weeks are 50, 60, 70, 60, 95 and 75 units. Setup cost is ₹200 per order and holding cost is ₹1 per unit per…
- An item has gross requirements of 40, 0, 60, 30, 0 and 80 units in weeks 1–6. On-hand stock is 50, a scheduled receipt of 20 arrives in…
- Five jobs go through machine M1 then M2. Times (hours) on M1, M2: A 5, 2; B 1, 6; C 9, 7; D 3, 8; E 10, 4. What sequence does Johnson's…
- Five jobs go through machine M1 then M2. Times (hours) on M1, M2: A 5, 2; B 1, 6; C 9, 7; D 3, 8; E 10, 4. Using the Johnson sequence…