Management & CommerceHardOps MT · Supply chain · MBA placement pattern
Net requirements over six weeks are 50, 60, 70, 60, 95 and 75 units. Setup cost is ₹200 per order and holding cost is ₹1 per unit per week, charged on ending inventory. Orders arrive at the start of the week they are needed. Using a periodic order quantity that covers two weeks per order, what is the total cost over the six weeks?
- A. ₹795
- B. ₹1,200
- C. ₹845
- D. ₹600
Correct answer: A. ₹795
Orders: week 1 (50 + 60 = 110), week 3 (70 + 60 = 130), week 5 (95 + 75 = 170). Ending inventory is 60 after weeks 1, 3 and 75 after week 5 (zero otherwise) → holding = 60 + 60 + 75 = ₹195. Setups = 3 × 200 = ₹600. Total ₹795. Lot-for-lot costs 6 × 200 = ₹1,200; a three-week POQ costs ₹845.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- An item has gross requirements of 40, 0, 60, 30, 0 and 80 units in weeks 1–6. On-hand stock is 50, a scheduled receipt of 20 arrives in…
- Five jobs go through machine M1 then M2. Times (hours) on M1, M2: A 5, 2; B 1, 6; C 9, 7; D 3, 8; E 10, 4. What sequence does Johnson's…
- Five jobs go through machine M1 then M2. Times (hours) on M1, M2: A 5, 2; B 1, 6; C 9, 7; D 3, 8; E 10, 4. Using the Johnson sequence…
- Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). What is the…
- Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). Compare SPT…
- Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). Using…