Management & CommerceVery hardOps MT · Supply chain · MBA placement pattern
Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). Using Moore–Hodgson's algorithm to minimise the number of tardy jobs, what is the minimum number of tardy jobs and which job is pushed to the end?
- A. 1; job R
- B. 2; jobs R and T
- C. 0; no job
- D. 1; job T
Correct answer: A. 1; job R
Start with EDD: Q, P, S, R, T → completions 2, 8, 11, 19, 28. The first tardy job is R (19 > 18). Remove the longest job so far (R, 8 days) and put it at the end. New schedule Q, P, S, T, R → completions 2, 8, 11, 20, 28: only R is late. Zero is impossible: Q, P, S and R are all due by day 18 but need 19 days of work together, so at least one of them must be late. Hence 1 is the minimum.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Four jobs pass through M1, M2 and M3 in that order. Times (hours): J1 8, 3, 6; J2 5, 4, 7; J3 6, 2, 5; J4 7, 5, 9. Using Johnson's rule…
- Today is day 20. Four jobs remain (due day; days of work left): A (30; 4), B (26; 8), C (32; 6), D (25; 3). Sequencing by critical ratio…
- Three markets with annual loads: M1 at (2, 8) with 300, M2 at (6, 2) with 200 and M3 at (9, 6) with 500. Distances are rectilinear. Site X…
- For jobs waiting at a single machine, all available at the start, which sequencing rule minimises the average flow time (and the average…
- Which statements about aggregate planning strategies are correct? I. A chase strategy keeps finished-goods inventory low. II. A level…
- Markets with annual loads: M1 at (2, 8) with 300, M2 at (6, 2) with 150 and M3 at (9, 6) with 550. Distances are rectilinear. What…