Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). Using Moore–Hodgson's algorithm to minimise the number of tardy jobs, what is the minimum number of tardy jobs and which job is pushed to the end?

  1. A. 1; job R
  2. B. 2; jobs R and T
  3. C. 0; no job
  4. D. 1; job T

Correct answer: A. 1; job R

Start with EDD: Q, P, S, R, T → completions 2, 8, 11, 19, 28. The first tardy job is R (19 > 18). Remove the longest job so far (R, 8 days) and put it at the end. New schedule Q, P, S, T, R → completions 2, 8, 11, 20, 28: only R is late. Zero is impossible: Q, P, S and R are all due by day 18 but need 19 days of work together, so at least one of them must be late. Hence 1 is the minimum.