Management & CommerceHardOps MT · Supply chain · MBA placement pattern
Today is day 20. Four jobs remain (due day; days of work left): A (30; 4), B (26; 8), C (32; 6), D (25; 3). Sequencing by critical ratio, lowest first, what is the order?
- A. D–B–A–C
- B. D–A–C–B
- C. B–D–C–A
- D. B–D–A–C
Correct answer: C. B–D–C–A
CR = (due − today) ÷ work left: A 10/4 = 2.5, B 6/8 = 0.75, C 12/6 = 2.0, D 5/3 ≈ 1.67. Ascending: B–D–C–A. EDD would give D–B–A–C and SPT D–A–C–B. B is already behind (CR < 1) despite not being due first.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Three markets with annual loads: M1 at (2, 8) with 300, M2 at (6, 2) with 200 and M3 at (9, 6) with 500. Distances are rectilinear. Site X…
- For jobs waiting at a single machine, all available at the start, which sequencing rule minimises the average flow time (and the average…
- Which statements about aggregate planning strategies are correct? I. A chase strategy keeps finished-goods inventory low. II. A level…
- Markets with annual loads: M1 at (2, 8) with 300, M2 at (6, 2) with 150 and M3 at (9, 6) with 550. Distances are rectilinear. What…
- Twenty units are life-tested for 1,000 hours each; any unit that fails is replaced at once, so the test covers 20,000 unit-hours, and 4…
- The first unit of a new aircraft sub-assembly took 100 labour hours. The work follows an 80% unit learning curve. How long should the 8th…