Today is day 20. Four jobs remain (due day; days of work left): A (30; 4), B (26; 8), C (32; 6), D (25; 3). Sequencing by critical ratio, lowest first, what is the order?

  1. A. D–B–A–C
  2. B. D–A–C–B
  3. C. B–D–C–A
  4. D. B–D–A–C

Correct answer: C. B–D–C–A

CR = (due − today) ÷ work left: A 10/4 = 2.5, B 6/8 = 0.75, C 12/6 = 2.0, D 5/3 ≈ 1.67. Ascending: B–D–C–A. EDD would give D–B–A–C and SPT D–A–C–B. B is already behind (CR < 1) despite not being due first.