Management & CommerceEasyOps MT · Supply chain · MBA placement pattern
For jobs waiting at a single machine, all available at the start, which sequencing rule minimises the average flow time (and the average number of jobs in the system)?
- A. Earliest due date (EDD)
- B. First come, first served (FCFS)
- C. Shortest processing time (SPT)
- D. Longest processing time (LPT)
Correct answer: C. Shortest processing time (SPT)
Putting short jobs first reduces the waiting added to every later job, so SPT minimises mean flow time on a single machine. EDD instead minimises maximum lateness; the makespan is the same for every order.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Which statements about aggregate planning strategies are correct? I. A chase strategy keeps finished-goods inventory low. II. A level…
- Markets with annual loads: M1 at (2, 8) with 300, M2 at (6, 2) with 150 and M3 at (9, 6) with 550. Distances are rectilinear. What…
- Twenty units are life-tested for 1,000 hours each; any unit that fails is replaced at once, so the test covers 20,000 unit-hours, and 4…
- The first unit of a new aircraft sub-assembly took 100 labour hours. The work follows an 80% unit learning curve. How long should the 8th…
- Unit 1 of a custom machine took 200 hours, and production follows an 85% unit learning curve. Approximately how many hours will unit 10…
- A contractor's first unit took 50 hours and work follows a 90% unit learning curve (Tₙ = T₁ × n^b, b = log 0.9 ÷ log 2 ≈ −0.152). Four…