A contractor's first unit took 50 hours and work follows a 90% unit learning curve (Tₙ = T₁ × n^b, b = log 0.9 ÷ log 2 ≈ −0.152). Four units are already built. Labour costs ₹400 an hour. What is the labour cost of the next four units (units 5 to 8), to the nearest hundred rupees?

  1. A. ≈ ₹60,400
  2. B. ≈ ₹58,300
  3. C. ≈ ₹71,100
  4. D. ₹80,000

Correct answer: A. ≈ ₹60,400

Unit times: T₅ ≈ 39.15, T₆ ≈ 38.08, T₇ ≈ 37.2, T₈ = 50 × 0.9³ = 36.45 hours. Sum ≈ 150.88 hours × ₹400 ≈ ₹60,400. Using T₈ for all four units understates it (≈ ₹58,300); units 1–4 cost about ₹71,100; ₹80,000 ignores learning altogether.