Management & CommerceVery hardOps MT · Supply chain · MBA placement pattern
A contractor's first unit took 50 hours and work follows a 90% unit learning curve (Tₙ = T₁ × n^b, b = log 0.9 ÷ log 2 ≈ −0.152). Four units are already built. Labour costs ₹400 an hour. What is the labour cost of the next four units (units 5 to 8), to the nearest hundred rupees?
- A. ≈ ₹60,400
- B. ≈ ₹58,300
- C. ≈ ₹71,100
- D. ₹80,000
Correct answer: A. ≈ ₹60,400
Unit times: T₅ ≈ 39.15, T₆ ≈ 38.08, T₇ ≈ 37.2, T₈ = 50 × 0.9³ = 36.45 hours. Sum ≈ 150.88 hours × ₹400 ≈ ₹60,400. Using T₈ for all four units understates it (≈ ₹58,300); units 1–4 cost about ₹71,100; ₹80,000 ignores learning altogether.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- On a learning-curve job, the 4th unit took 72 hours and the 16th unit took 46.08 hours. What is the learning rate?
- A cooling system has a controller (reliability 0.98) in series with a pair of identical pumps in parallel, each with reliability 0.90; the…
- A packing line has three stages in series: a feeder (reliability 0.95), a sealing stage with two identical sealers in parallel (each 0.80…
- A critical sensor has reliability 0.85. Identical sensors can be installed in parallel (the stage works if at least one works). What is…
- A buyer uses a single sampling plan: inspect n = 20 items from each lot and accept the lot if at most c = 1 is defective. If a lot is 5%…
- Lots of N = 1,000 are checked with the plan n = 20, c = 1. Rejected lots are screened 100% and all defectives replaced; in accepted lots…