On a learning-curve job, the 4th unit took 72 hours and the 16th unit took 46.08 hours. What is the learning rate?

  1. A. 64%
  2. B. 90%
  3. C. 80%
  4. D. 85%

Correct answer: C. 80%

From unit 4 to unit 16 there are two doublings (4 → 8 → 16). So rate² = 46.08 ÷ 72 = 0.64, and rate = 0.8, i.e. 80%. Taking 0.64 itself as the rate forgets that two doublings occurred.