Management & CommerceModerateOps MT · Supply chain · MBA placement pattern
Which statements about aggregate planning strategies are correct? I. A chase strategy keeps finished-goods inventory low. II. A level strategy suits firms whose hiring and layoff costs are high. III. A chase strategy suits work that needs highly skilled, hard-to-hire staff. IV. A level strategy builds inventory in slack periods to cover peak demand.
- A. I, II and IV only
- B. I and III only
- C. II, III and IV only
- D. All four
Correct answer: A. I, II and IV only
Chase changes output (often the workforce) to match demand, so little stock is built (I). Level keeps output steady, building stock in slack periods (IV), which pays when changing the workforce is costly (II). Hiring and firing skilled staff each period is exactly what a chase plan does badly, so III is false.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Markets with annual loads: M1 at (2, 8) with 300, M2 at (6, 2) with 150 and M3 at (9, 6) with 550. Distances are rectilinear. What…
- Twenty units are life-tested for 1,000 hours each; any unit that fails is replaced at once, so the test covers 20,000 unit-hours, and 4…
- The first unit of a new aircraft sub-assembly took 100 labour hours. The work follows an 80% unit learning curve. How long should the 8th…
- Unit 1 of a custom machine took 200 hours, and production follows an 85% unit learning curve. Approximately how many hours will unit 10…
- A contractor's first unit took 50 hours and work follows a 90% unit learning curve (Tₙ = T₁ × n^b, b = log 0.9 ÷ log 2 ≈ −0.152). Four…
- On a learning-curve job, the 4th unit took 72 hours and the 16th unit took 46.08 hours. What is the learning rate?