The first unit of a new aircraft sub-assembly took 100 labour hours. The work follows an 80% unit learning curve. How long should the 8th unit take?

  1. A. 64 hours
  2. B. 51.2 hours
  3. C. 40.96 hours
  4. D. 80 hours

Correct answer: B. 51.2 hours

Each doubling of cumulative output multiplies unit time by 0.8. Unit 8 is three doublings from unit 1: 100 × 0.8³ = 51.2 hours. 64 hours is unit 4 and 40.96 hours is unit 16.