Management & CommerceModerateOps MT · Supply chain · MBA placement pattern
The first unit of a new aircraft sub-assembly took 100 labour hours. The work follows an 80% unit learning curve. How long should the 8th unit take?
- A. 64 hours
- B. 51.2 hours
- C. 40.96 hours
- D. 80 hours
Correct answer: B. 51.2 hours
Each doubling of cumulative output multiplies unit time by 0.8. Unit 8 is three doublings from unit 1: 100 × 0.8³ = 51.2 hours. 64 hours is unit 4 and 40.96 hours is unit 16.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Unit 1 of a custom machine took 200 hours, and production follows an 85% unit learning curve. Approximately how many hours will unit 10…
- A contractor's first unit took 50 hours and work follows a 90% unit learning curve (Tₙ = T₁ × n^b, b = log 0.9 ÷ log 2 ≈ −0.152). Four…
- On a learning-curve job, the 4th unit took 72 hours and the 16th unit took 46.08 hours. What is the learning rate?
- A cooling system has a controller (reliability 0.98) in series with a pair of identical pumps in parallel, each with reliability 0.90; the…
- A packing line has three stages in series: a feeder (reliability 0.95), a sealing stage with two identical sealers in parallel (each 0.80…
- A critical sensor has reliability 0.85. Identical sensors can be installed in parallel (the stage works if at least one works). What is…