Unit 1 of a custom machine took 200 hours, and production follows an 85% unit learning curve. Approximately how many hours will unit 10 take? (Use Tₙ = T₁ × n^b with b = log 0.85 ÷ log 2.)

  1. A. 104.4 hours
  2. B. 122.8 hours
  3. C. 170.0 hours
  4. D. 116.6 hours

Correct answer: D. 116.6 hours

b = log 0.85 ÷ log 2 ≈ -0.2345. T₁₀ = 200 × 10^(-0.2345) ≈ 200 × 0.5828 ≈ 116.6 hours. 122.8 is unit 8 (three doublings) and 104.4 is unit 16 (four doublings); 170 applies the 85% only once.