Unit 1 of a custom machine took 200 hours, and production follows an 85% unit learning curve. Approximately how many hours will unit 10 take? (Use Tₙ = T₁ × n^b with b = log 0.85 ÷ log 2.)
- A. 104.4 hours
- B. 122.8 hours
- C. 170.0 hours
- D. 116.6 hours
Correct answer: D. 116.6 hours
b = log 0.85 ÷ log 2 ≈ -0.2345. T₁₀ = 200 × 10^(-0.2345) ≈ 200 × 0.5828 ≈ 116.6 hours. 122.8 is unit 8 (three doublings) and 104.4 is unit 16 (four doublings); 170 applies the 85% only once.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A contractor's first unit took 50 hours and work follows a 90% unit learning curve (Tₙ = T₁ × n^b, b = log 0.9 ÷ log 2 ≈ −0.152). Four…
- On a learning-curve job, the 4th unit took 72 hours and the 16th unit took 46.08 hours. What is the learning rate?
- A cooling system has a controller (reliability 0.98) in series with a pair of identical pumps in parallel, each with reliability 0.90; the…
- A packing line has three stages in series: a feeder (reliability 0.95), a sealing stage with two identical sealers in parallel (each 0.80…
- A critical sensor has reliability 0.85. Identical sensors can be installed in parallel (the stage works if at least one works). What is…
- A buyer uses a single sampling plan: inspect n = 20 items from each lot and accept the lot if at most c = 1 is defective. If a lot is 5%…