Three markets with annual loads: M1 at (2, 8) with 300, M2 at (6, 2) with 200 and M3 at (9, 6) with 500. Distances are rectilinear. Site X is at (5, 5) and site Y at (7, 6). Which site has the lower total load × distance, and by how much?
- A. X, by 1,000
- B. Y, by 527
- C. Y, by 600
- D. Y, by 1,000
Correct answer: D. Y, by 1,000
X: 300 × (3 + 3) + 200 × (1 + 3) + 500 × (4 + 1) = 1,800 + 800 + 2,500 = 5,100. Y: 300 × (5 + 2) + 200 × (1 + 4) + 500 × (2 + 0) = 2,100 + 1,000 + 1,000 = 4,100. Y wins by 1,000. Straight-line distances would give a gap of about 527 instead.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- For jobs waiting at a single machine, all available at the start, which sequencing rule minimises the average flow time (and the average…
- Which statements about aggregate planning strategies are correct? I. A chase strategy keeps finished-goods inventory low. II. A level…
- Markets with annual loads: M1 at (2, 8) with 300, M2 at (6, 2) with 150 and M3 at (9, 6) with 550. Distances are rectilinear. What…
- Twenty units are life-tested for 1,000 hours each; any unit that fails is replaced at once, so the test covers 20,000 unit-hours, and 4…
- The first unit of a new aircraft sub-assembly took 100 labour hours. The work follows an 80% unit learning curve. How long should the 8th…
- Unit 1 of a custom machine took 200 hours, and production follows an 85% unit learning curve. Approximately how many hours will unit 10…