Management & CommerceVery hardOps MT · Supply chain · MBA placement pattern
Four jobs pass through M1, M2 and M3 in that order. Times (hours): J1 8, 3, 6; J2 5, 4, 7; J3 6, 2, 5; J4 7, 5, 9. Using Johnson's rule extended to three machines (check its condition first), what are the sequence and the makespan?
- A. J2–J4–J1–J3; 40 hours
- B. J2–J4–J1–J3; 37 hours
- C. J3–J2–J4–J1; 37 hours
- D. J1–J2–J3–J4; 40 hours
Correct answer: B. J2–J4–J1–J3; 37 hours
Condition: min M1 time (5) ≥ max M2 time (5), so the method applies. Form G = M1 + M2 and H = M2 + M3: J1 (11, 9), J2 (9, 11), J3 (8, 7), J4 (12, 14). Johnson on (G, H): J3's 7 (H) → last; J2's 9 (G) → first; J1's 9 (H) → second last; J4 in the middle → J2–J4–J1–J3. Simulating: M3 completes at 37 hours (no order does better). The natural order J1–J4 takes 40 hours.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Today is day 20. Four jobs remain (due day; days of work left): A (30; 4), B (26; 8), C (32; 6), D (25; 3). Sequencing by critical ratio…
- Three markets with annual loads: M1 at (2, 8) with 300, M2 at (6, 2) with 200 and M3 at (9, 6) with 500. Distances are rectilinear. Site X…
- For jobs waiting at a single machine, all available at the start, which sequencing rule minimises the average flow time (and the average…
- Which statements about aggregate planning strategies are correct? I. A chase strategy keeps finished-goods inventory low. II. A level…
- Markets with annual loads: M1 at (2, 8) with 300, M2 at (6, 2) with 150 and M3 at (9, 6) with 550. Distances are rectilinear. What…
- Twenty units are life-tested for 1,000 hours each; any unit that fails is replaced at once, so the test covers 20,000 unit-hours, and 4…