Four jobs pass through M1, M2 and M3 in that order. Times (hours): J1 8, 3, 6; J2 5, 4, 7; J3 6, 2, 5; J4 7, 5, 9. Using Johnson's rule extended to three machines (check its condition first), what are the sequence and the makespan?

  1. A. J2–J4–J1–J3; 40 hours
  2. B. J2–J4–J1–J3; 37 hours
  3. C. J3–J2–J4–J1; 37 hours
  4. D. J1–J2–J3–J4; 40 hours

Correct answer: B. J2–J4–J1–J3; 37 hours

Condition: min M1 time (5) ≥ max M2 time (5), so the method applies. Form G = M1 + M2 and H = M2 + M3: J1 (11, 9), J2 (9, 11), J3 (8, 7), J4 (12, 14). Johnson on (G, H): J3's 7 (H) → last; J2's 9 (G) → first; J1's 9 (H) → second last; J4 in the middle → J2–J4–J1–J3. Simulating: M3 completes at 37 hours (no order does better). The natural order J1–J4 takes 40 hours.