Five jobs go through machine M1 then M2. Times (hours) on M1, M2: A 5, 2; B 1, 6; C 9, 7; D 3, 8; E 10, 4. Using the Johnson sequence, what is the makespan and by how many hours does it beat processing the jobs in the order A–B–C–D–E?
- A. 34 hours; 4 hours shorter
- B. 30 hours; 3 hours shorter
- C. 30 hours; 4 hours shorter
- D. 28 hours; 6 hours shorter
Correct answer: C. 30 hours; 4 hours shorter
Sequence B–D–C–E–A. M1 finishes at 1, 4, 13, 23, 28. M2: B 1–7, D 7–15, C 15–22, E 23–27, A 28–30 → makespan 30. In order A–B–C–D–E, M1 ends 5, 6, 15, 18, 28 and M2: 5–7, 7–13, 15–22, 22–30, 30–34 → 34. Saving = 4 hours. (M2 idles 3 hours under Johnson — that is not the saving.)
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). What is the…
- Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). Compare SPT…
- Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). Using…
- Four jobs pass through M1, M2 and M3 in that order. Times (hours): J1 8, 3, 6; J2 5, 4, 7; J3 6, 2, 5; J4 7, 5, 9. Using Johnson's rule…
- Today is day 20. Four jobs remain (due day; days of work left): A (30; 4), B (26; 8), C (32; 6), D (25; 3). Sequencing by critical ratio…
- Three markets with annual loads: M1 at (2, 8) with 300, M2 at (6, 2) with 200 and M3 at (9, 6) with 500. Distances are rectilinear. Site X…