Five jobs go through machine M1 then M2. Times (hours) on M1, M2: A 5, 2; B 1, 6; C 9, 7; D 3, 8; E 10, 4. Using the Johnson sequence, what is the makespan and by how many hours does it beat processing the jobs in the order A–B–C–D–E?

  1. A. 34 hours; 4 hours shorter
  2. B. 30 hours; 3 hours shorter
  3. C. 30 hours; 4 hours shorter
  4. D. 28 hours; 6 hours shorter

Correct answer: C. 30 hours; 4 hours shorter

Sequence B–D–C–E–A. M1 finishes at 1, 4, 13, 23, 28. M2: B 1–7, D 7–15, C 15–22, E 23–27, A 28–30 → makespan 30. In order A–B–C–D–E, M1 ends 5, 6, 15, 18, 28 and M2: 5–7, 7–13, 15–22, 22–30, 30–34 → 34. Saving = 4 hours. (M2 idles 3 hours under Johnson — that is not the saving.)