Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). Compare SPT and EDD. Which statements are correct? I. SPT gives the lower average flow time. II. EDD gives the lower total tardiness. III. Both rules give the same makespan. IV. EDD leaves no job tardy.
- A. I, II and III only
- B. I and II only
- C. I, III and IV only
- D. II, III and IV only
Correct answer: A. I, II and III only
SPT (Q, S, P, R, T): completions 2, 5, 11, 19, 28 → flow 13.0, tardiness 0, 0, 1, 1, 5 = 7 (3 tardy jobs). EDD (Q, P, S, R, T): completions 2, 8, 11, 19, 28 → flow 13.6, tardiness 0, 0, 0, 1, 5 = 6 (2 tardy jobs). Makespan is 28 for any order. IV fails because R and T are still late.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). Using…
- Four jobs pass through M1, M2 and M3 in that order. Times (hours): J1 8, 3, 6; J2 5, 4, 7; J3 6, 2, 5; J4 7, 5, 9. Using Johnson's rule…
- Today is day 20. Four jobs remain (due day; days of work left): A (30; 4), B (26; 8), C (32; 6), D (25; 3). Sequencing by critical ratio…
- Three markets with annual loads: M1 at (2, 8) with 300, M2 at (6, 2) with 200 and M3 at (9, 6) with 500. Distances are rectilinear. Site X…
- For jobs waiting at a single machine, all available at the start, which sequencing rule minimises the average flow time (and the average…
- Which statements about aggregate planning strategies are correct? I. A chase strategy keeps finished-goods inventory low. II. A level…