Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). Compare SPT and EDD. Which statements are correct? I. SPT gives the lower average flow time. II. EDD gives the lower total tardiness. III. Both rules give the same makespan. IV. EDD leaves no job tardy.

  1. A. I, II and III only
  2. B. I and II only
  3. C. I, III and IV only
  4. D. II, III and IV only

Correct answer: A. I, II and III only

SPT (Q, S, P, R, T): completions 2, 5, 11, 19, 28 → flow 13.0, tardiness 0, 0, 1, 1, 5 = 7 (3 tardy jobs). EDD (Q, P, S, R, T): completions 2, 8, 11, 19, 28 → flow 13.6, tardiness 0, 0, 0, 1, 5 = 6 (2 tardy jobs). Makespan is 28 for any order. IV fails because R and T are still late.