Management & CommerceModerateOps MT · Supply chain · MBA placement pattern

Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). What is the average flow time under the SPT rule?

  1. A. 13.6 days
  2. B. 13 days
  3. C. 5.6 days
  4. D. 28 days

Correct answer: B. 13 days

SPT order Q, S, P, R, T: completions 2, 5, 11, 19, 28. Average flow time = 65 ÷ 5 = 13 days. EDD (Q, P, S, R, T) gives 13.6; 5.6 is the mean processing time and 28 is the makespan.