Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). What is the average flow time under the SPT rule?
- A. 13.6 days
- B. 13 days
- C. 5.6 days
- D. 28 days
Correct answer: B. 13 days
SPT order Q, S, P, R, T: completions 2, 5, 11, 19, 28. Average flow time = 65 ÷ 5 = 13 days. EDD (Q, P, S, R, T) gives 13.6; 5.6 is the mean processing time and 28 is the makespan.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). Compare SPT…
- Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). Using…
- Four jobs pass through M1, M2 and M3 in that order. Times (hours): J1 8, 3, 6; J2 5, 4, 7; J3 6, 2, 5; J4 7, 5, 9. Using Johnson's rule…
- Today is day 20. Four jobs remain (due day; days of work left): A (30; 4), B (26; 8), C (32; 6), D (25; 3). Sequencing by critical ratio…
- Three markets with annual loads: M1 at (2, 8) with 300, M2 at (6, 2) with 200 and M3 at (9, 6) with 500. Distances are rectilinear. Site X…
- For jobs waiting at a single machine, all available at the start, which sequencing rule minimises the average flow time (and the average…