Management & CommerceVery hardOps MT · Supply chain · MBA placement pattern

An item has gross requirements of 40, 0, 60, 30, 0 and 80 units in weeks 1–6. On-hand stock is 50, a scheduled receipt of 20 arrives in week 3, the lot size is a fixed 50 units (more lots if needed), lead time is 2 weeks and safety stock is zero. What are the planned order releases, and what is the projected on-hand at the end of week 6?

  1. A. Weeks 3, 4 and 6 (50 each); 10 units
  2. B. Weeks 1, 2 and 4 (50, 50, 100); 40 units
  3. C. Weeks 1, 2 and 4 (50 each); 10 units
  4. D. Weeks 2, 3 and 5 (50 each); 10 units

Correct answer: C. Weeks 1, 2 and 4 (50 each); 10 units

Projected on-hand: wk1 10, wk2 10, wk3 10 + 20 − 60 = −30 → receive 50 → 20, wk4 20 − 30 = −10 → receive 50 → 40, wk5 40, wk6 40 − 80 = −40 → receive 50 → 10. Planned receipts in weeks 3, 4, 6 are released 2 weeks earlier: weeks 1, 2, 4. Ignoring the scheduled receipt forces 100 in week 6 and leaves 40; listing the receipt weeks forgets the lead-time offset.

More Operations, Supply Chain & Business Analytics questions

Exams that ask this topic