Management & CommerceVery hardOps MT · Supply chain · MBA placement pattern
An item has gross requirements of 40, 0, 60, 30, 0 and 80 units in weeks 1–6. On-hand stock is 50, a scheduled receipt of 20 arrives in week 3, the lot size is a fixed 50 units (more lots if needed), lead time is 2 weeks and safety stock is zero. What are the planned order releases, and what is the projected on-hand at the end of week 6?
- A. Weeks 3, 4 and 6 (50 each); 10 units
- B. Weeks 1, 2 and 4 (50, 50, 100); 40 units
- C. Weeks 1, 2 and 4 (50 each); 10 units
- D. Weeks 2, 3 and 5 (50 each); 10 units
Correct answer: C. Weeks 1, 2 and 4 (50 each); 10 units
Projected on-hand: wk1 10, wk2 10, wk3 10 + 20 − 60 = −30 → receive 50 → 20, wk4 20 − 30 = −10 → receive 50 → 40, wk5 40, wk6 40 − 80 = −40 → receive 50 → 10. Planned receipts in weeks 3, 4, 6 are released 2 weeks earlier: weeks 1, 2, 4. Ignoring the scheduled receipt forces 100 in week 6 and leaves 40; listing the receipt weeks forgets the lead-time offset.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Five jobs go through machine M1 then M2. Times (hours) on M1, M2: A 5, 2; B 1, 6; C 9, 7; D 3, 8; E 10, 4. What sequence does Johnson's…
- Five jobs go through machine M1 then M2. Times (hours) on M1, M2: A 5, 2; B 1, 6; C 9, 7; D 3, 8; E 10, 4. Using the Johnson sequence…
- Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). What is the…
- Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). Compare SPT…
- Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). Using…
- Four jobs pass through M1, M2 and M3 in that order. Times (hours): J1 8, 3, 6; J2 5, 4, 7; J3 6, 2, 5; J4 7, 5, 9. Using Johnson's rule…