Management & CommerceModerateOps MT · Supply chain · MBA placement pattern
Five jobs go through machine M1 then M2. Times (hours) on M1, M2: A 5, 2; B 1, 6; C 9, 7; D 3, 8; E 10, 4. What sequence does Johnson's rule give?
- A. A–E–C–D–B
- B. B–D–E–C–A
- C. B–A–D–C–E
- D. B–D–C–E–A
Correct answer: D. B–D–C–E–A
Pick the smallest remaining time: B's 1 (on M1) → first; A's 2 (on M2) → last; D's 3 (M1) → second; E's 4 (M2) → second last; C fills the middle. Sequence B–D–C–E–A.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Five jobs go through machine M1 then M2. Times (hours) on M1, M2: A 5, 2; B 1, 6; C 9, 7; D 3, 8; E 10, 4. Using the Johnson sequence…
- Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). What is the…
- Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). Compare SPT…
- Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). Using…
- Four jobs pass through M1, M2 and M3 in that order. Times (hours): J1 8, 3, 6; J2 5, 4, 7; J3 6, 2, 5; J4 7, 5, 9. Using Johnson's rule…
- Today is day 20. Four jobs remain (due day; days of work left): A (30; 4), B (26; 8), C (32; 6), D (25; 3). Sequencing by critical ratio…