Management & CommerceModerateOps MT · Supply chain · MBA placement pattern

Five jobs go through machine M1 then M2. Times (hours) on M1, M2: A 5, 2; B 1, 6; C 9, 7; D 3, 8; E 10, 4. What sequence does Johnson's rule give?

  1. A. A–E–C–D–B
  2. B. B–D–E–C–A
  3. C. B–A–D–C–E
  4. D. B–D–C–E–A

Correct answer: D. B–D–C–E–A

Pick the smallest remaining time: B's 1 (on M1) → first; A's 2 (on M2) → last; D's 3 (M1) → second; E's 4 (M2) → second last; C fills the middle. Sequence B–D–C–E–A.