Management & CommerceHardOps MT · Supply chain · MBA placement pattern
Product A needs 2 units of B and 3 units of C. Each B needs 2 units of D; each C needs 1 unit of D and 4 units of E. An order for 50 A arrives. On hand: 20 B, 0 C and 30 D. What is the net requirement of D?
- A. 320
- B. 280
- C. 310
- D. 350
Correct answer: B. 280
Net B = 2 × 50 − 20 = 80; net C = 3 × 50 = 150. Gross D = 2 × 80 + 1 × 150 = 310; net D = 310 − 30 = 280. Ignoring the B on hand gives gross D of 350 and net 320; forgetting the D on hand leaves 310.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Each unit of X needs 2 Y and 1 Z. Each Y needs 3 W. Each Z needs 2 W and 1 Y. With no stock on hand, how many units of W are needed for 40…
- Net requirements over six weeks are 50, 60, 70, 60, 95 and 75 units. Setup cost is ₹200 per order and holding cost is ₹1 per unit per…
- An item has gross requirements of 40, 0, 60, 30, 0 and 80 units in weeks 1–6. On-hand stock is 50, a scheduled receipt of 20 arrives in…
- Five jobs go through machine M1 then M2. Times (hours) on M1, M2: A 5, 2; B 1, 6; C 9, 7; D 3, 8; E 10, 4. What sequence does Johnson's…
- Five jobs go through machine M1 then M2. Times (hours) on M1, M2: A 5, 2; B 1, 6; C 9, 7; D 3, 8; E 10, 4. Using the Johnson sequence…
- Five jobs wait at one machine (processing days; due day, all available now): P 6 (10), Q 2 (6), R 8 (18), S 3 (15), T 9 (23). What is the…