A dimension has specification 50 ± 3 mm, and the process mean is 50.5 mm. What is the largest process standard deviation that still gives Cpk = 1.33?
- A. About 0.752 mm
- B. About 0.627 mm
- C. About 0.877 mm
- D. About 0.501 mm
Correct answer: B. About 0.627 mm
The nearer limit is USL = 53, 2.5 mm from the mean. Cpk = 2.5/(3σ) ≥ 1.33 gives σ ≤ 2.5/3.99 ≈ 0.627. Using the full half-width of 3 mm (a Cp calculation) gives 0.752; using the far limit 3.5 mm gives 0.877.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- For an in-control process using 3-sigma limits, about how many samples will be plotted, on average, before a false out-of-control signal?
- An X̄ chart with 3-sigma limits uses samples of n = 4. The process mean suddenly shifts up by one process standard deviation (1σ). What is…
- Daily demand is independent from day to day and lead time is constant. If the supplier's lead time doubles from 8 to 16 days, with the…
- A plant needs to produce 5,000 units of P (1.2 machine-hours each) and 8,000 units of Q (0.75 machine-hours each) a year, plus a setup…
- An online lender approves 400 loans a week and has, on average, 1,000 applications in process. It wants to grow to 600 approvals a week…
- A firm's accounts receivable average ₹90 lakh, and credit sales are ₹6 crore a year (360 days). It wants to cut average receivables to ₹60…