In the Hungarian method for a 5 × 5 assignment problem, after row and column reductions all zeros can be covered by 4 lines. What does this mean?
- A. The current zeros already give an optimal assignment of all five jobs
- B. The problem is infeasible, since one row has no independent zero
- C. One job must be left unassigned, as only four lines are needed
- D. Not yet optimal; revise with the smallest uncovered element
Correct answer: D. Not yet optimal; revise with the smallest uncovered element
Optimality needs the minimum number of covering lines to equal n (5). With 4 lines, subtract the smallest uncovered value from uncovered cells, add it at the intersections, and repeat.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A plant runs at 80% utilisation and its average queue of jobs is 4 hours of work. Management plans to load it to 95% utilisation. Assuming…
- A supply chain shares point-of-sale data and builds a joint forecast with its retailer, agreeing on replenishment plans together. Which…
- A lean programme wants to halve a part's economic lot size without changing demand or holding cost. By how much must the setup (ordering)…
- A part is made in lots of 1,200 at a production rate of 100 per day, while it is used at 40 per day throughout the year. In each…
- Three stations in series each take 1 minute per unit. A batch of 50 units moves from station to station only when the whole batch is done…
- An audit of 2,000 invoices finds 96 errors. Each invoice has 8 distinct fields where an error can occur. What is the DPMO?