Quantitative AptitudeModerateSSC CGL · RRB NTPC · IBPS

8 workers can build a wall in 12 days. How many days will 24 workers (working at the same rate) take?

  1. A. 6 days
  2. B. 36 days
  3. C. 4 days
  4. D. 17 days

Correct answer: C. 4 days

Total work = 8 × 12 = 96 man-days. With 24 workers: 96/24 = 4 days.