CS FundamentalsHardCognizant · Accenture · Scrum interview
In the 2020 Scrum Guide each artifact has a commitment. Which pairing is correct?
- A. Product Backlog - Definition of Done; Sprint Backlog - Product Goal; Increment - Sprint Goal
- B. Product Backlog - Product Goal; Sprint Backlog - Sprint Goal; Increment - Definition of Done
- C. Product Backlog - Sprint Goal; Sprint Backlog - Definition of Done; Increment - Product Goal
- D. Product Backlog - Product Goal; Sprint Backlog - Definition of Done; Increment - Sprint Goal
Correct answer: B. Product Backlog - Product Goal; Sprint Backlog - Sprint Goal; Increment - Definition of Done
The Product Goal anchors the Product Backlog, the Sprint Goal anchors the Sprint Backlog, and the Definition of Done is the commitment that turns work into an Increment.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Midway through a sprint, a market change makes the Sprint Goal obsolete. According to the Scrum Guide, who can cancel the sprint?
- At the end of a sprint, one backlog item is coded but its automated tests, required by the Definition of Done, are not written. What does…
- A sprint commitment had stories of 8, 5, 5, 3 and 3 points. At the sprint's end the 8, one 5 and both 3s meet the Definition of Done; the…
- Mid-sprint, the Product Owner asks the Developers to also add a small new item. The Sprint Goal is not at risk. What does Scrum allow?
- For a one-month sprint the Scrum Guide sets maximum timeboxes of 8 hours for Sprint Planning, 4 hours for the Sprint Review and 3 hours…
- How many of these are Extreme Programming (XP) practices: (1) pair programming, (2) collective code ownership, (3) continuous integration…