CS FundamentalsHardCognizant · Capgemini · Scrum interview
Midway through a sprint, a market change makes the Sprint Goal obsolete. According to the Scrum Guide, who can cancel the sprint?
- A. The Scrum Master
- B. The Developers, by majority vote
- C. Only the Product Owner
- D. The project sponsor or senior management
Correct answer: C. Only the Product Owner
Only the Product Owner has the authority to cancel a sprint, and only when its goal becomes obsolete. Others can influence the decision, but the Scrum Master facilitates rather than decides.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- At the end of a sprint, one backlog item is coded but its automated tests, required by the Definition of Done, are not written. What does…
- A sprint commitment had stories of 8, 5, 5, 3 and 3 points. At the sprint's end the 8, one 5 and both 3s meet the Definition of Done; the…
- Mid-sprint, the Product Owner asks the Developers to also add a small new item. The Sprint Goal is not at risk. What does Scrum allow?
- For a one-month sprint the Scrum Guide sets maximum timeboxes of 8 hours for Sprint Planning, 4 hours for the Sprint Review and 3 hours…
- How many of these are Extreme Programming (XP) practices: (1) pair programming, (2) collective code ownership, (3) continuous integration…
- A backlog contains: 'As a developer, I want to create the database tables for orders.' Which INVEST criterion does it most clearly fail…